Breaking News :   Will not send Dr Sahib empty-handed: Ruhullah reacts to Farooq’s resignation challenge | Kishtwar minor death case: NCST likely to step in, team may visit Chatroo soon | CM Omar calls for shared responsibility to shape future of J&K children | 1998 Wandhama Massacre: SIA re-opens investigation into killings of 23 KPs | Rape accused who escaped police custody arrested in Jammu | DGP Prabhat reviews security preparedness for Eid Milad, Raksha Bandhan | Recruitment rules obsolete, redundant, need urgent revision: JKPSC | Land records go digital, farmer services get smarter | The road to developed India begins in the classroom | Expensive Treatment, A Heavy Burden on Life | Step In A Right Direction | 184 Armed Police personnel granted in-Situ Promotion | Satish Sharma extends Eid-e-Milad-un-Nabi (SAW) greetings | Major Turning Point In India's Digital Payment Journey: PM Modi On 10 Years Of UPI | Court acquits brother-in-law, family in rape-dowry case; slams 'One-Sided, Perfunctory' probe | Govt to sell onions at Rs 35/Kg in Delhi; 1st 'Kanda Express' with 800 Tn supply to reach on Wed | Two suspected over ground workers of terrorists arrested in J&K | NHAI clarifies incident at package-15 of Delhi-Amritsar-Katra Expressway near Jakh, Samba | Annual Kousar Nag Yatra-2026 concludes with participation of over 800 devotees | H1N1 Rise: Children, Elderly People At Most Risk, Doctors Warn | Labourer crushed to death as bridge pier collapses in Jammu | "Women's empowerment is one of main priorities of Omar Abdullah-led Government: RL Gupta | Anil Gupta, Senior Vice President JCCI flags tariff hike, warns of industry closures and job losses | From Haridwar to Udhampur: Rakshan Sharma carries Ganga Water, spreads message to protect Devika | Er Kiran Wattal Conferred Lifetime Achievement Award at International Excellence Awards | Arvind Gupta reviews PHE Works, pushes comprehensive water security plan for Jammu west | MIER College organises guest lecture on ALIMCO scheme and Disability Welfare Benefits | DC Udhampur chairs DDMA meeting; reviews restoration works in rain affected areas | DC directs for civic improvements ahead of Eid-e-Milad-un-Nabi, Raksha Bandhan | District Zoonosis Committee meeting held | Indian Army conducted medical health camp at Himote, Doda | Workshop on Aquifer Mapping, Groundwater Management held at Kathua | Swachhata Sankalp campaign held in Bhaderwah | DDC reviews progress of JJM Schemes in Doda | Back Issues  
 
news details
Pragati Portal: A Game Changer in Accelerating India’s Dedicated Freight Corridor Project
1/7/2026 9:49:25 PM
R K Jain

Dedicated Freight Corridor (DFC) Project is one of the most ambitious rail infrastructure initiatives undertaken since Independence. Designed to provide a high-capacity, technology-enabled rail corridor for freight transportation, the DFC aims to help Indian Railways regain its freight market share by offering faster, safer, more reliable and cost-effective logistics solutions. The project is also expected to catalyse the development of multimodal logistics parks, thereby reducing logistics costs and improving efficiency across the supply chain.
With an estimated cost of over ₹1.2 lakh crore and a total length of 2843 km, the DFC has two major arms:
Eastern Dedicated Freight Corridor (EDFC):
1337 kmStretching from Sahnewal (Ludhiana) in Punjab to Sonnagar in Bihar, the corridor passes through Punjab, Haryana, Uttar Pradesh and Bihar
Western Dedicated Freight Corridor (WDFC):
1506 km Stretching from Dadri in Uttar Pradesh to Jawaharlal Nehru Port Trust (JNPT) near Mumbai, it traverses Haryana, Rajasthan, Gujarat, Maharashtra and Uttar Pradesh.
Together, the DFC alignment passes through 7 states and 56 districts, cutting across forest areas, wildlife sanctuaries, mangrove stretches and creek zones — making project execution inherently complex.
Challenges That Threatened Timely Completion
Although the project was initiated in 2008, progress was hampered for several years due to multiple bottlenecks:
• Acquisition of about 11,000 hectares of land, including removal of structures and encroachments.
• Obtaining statutory clearances for forest land, wildlife sanctuaries, mangroves, tree cutting, creek crossings, etc.
• Elimination of over 900 level crossings through construction of Road Over Bridges (ROBs) and Road Under Bridges (RUBs), each requiring joint GAD approvals and land acquisition for approaches.
• Shifting of high-tension electric lines, gas and oil pipelines.
• Approvals from Defence authorities, NHAI, state highways, irrigation departments for canal crossings, and permissions for earth borrowing.
• Post-COVID financial stress on contractors, leading to poor cash flows.
The absence of encumbrance-free land severely impacted construction schedules and exposed the project to potential claims.
Pragati Portal – The Turning Point
The launch of the Pragati Portal by the Prime Minister’s Office (PMO) proved to be a watershed moment for the DFC Project.
Through the portal, unresolved issues were uploaded with detailed documentation by DFC officials. What made Pragati truly powerful was the visibility and accountability it created: concerned ministries, state governments and authorities knew that progress was being monitored at the highest level, including by the Hon’ble Prime Minister himself.
Issues that had remained pending for years despite relentless follow-ups were resolved within weeks — sometimes even days. In cases where immediate compliance was not feasible, authorities committed to firm target dates, which were then rigorously adhered to.
A New Culture of Governance and Accountability
The Pragati Portal emerged as a highly effective platform for:
• Real-time project monitoring
• Escalation of issues across multiple tiers simultaneously
• Inter-ministerial and inter-state coordination through a single window
Within DFC, a similar internal monitoring framework was institutionalised. Weekly reviews of major contracts, intensive site visits and continuous tracking of committed milestones became the norm. Since all timelines placed on the portal were on record, it also instilled a sense of responsibility within the project team to honour its commitments.
Tangible Impact on Project Execution
The faster resolution of complex issues significantly boosted construction progress and safeguarded the organisation from potential claims arising out of delays in providing encumbrance-free land. More importantly, Pragati transformed the overall governance culture by embedding transparency, responsiveness and accountability into day-to-day project management.
Conclusion
The Pragati Portal stands today as a live example of effective digital governance in action. For a mega project like the Dedicated Freight Corridor — cutting across multiple states, departments and regulatory jurisdictions — Pragati proved to be not just a monitoring tool, but a catalyst for change.
By ensuring faster decision-making, reducing inter-departmental friction, and enforcing accountability at every level, Pragati has played a decisive role in steering the DFC Project towards successful and timely completion, while setting a benchmark for future infrastructure programmes in India.
(The author is Former MD, DFCCIL)
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU