JAMMU MAY 10: Chief Engineer Elect. Maintt. & R.E Wing Jammu has informed that, in order to carry out branch cutting, repair/ maintenance of 33 KV line, the shutdown of 33 KV Janipur-Roop Nagar (BH-1)/New Subash Nagar line and 33 KV line is being observed.
During the shutdown, the power supply to Roop Nagar, Lower Roop Nagar, Colony, Chinor, Durga Nagar, Buta Nagar, Ploura, Patoli, Shant Nagar, Vivek Vihar, Pandotha Colony and adjoining areas will remain affected on May 12 from 9 am to 2 pm.
Similarly, the power supply to Janipur Colony, Patoli, High Court, Hari Nagar, Tali Morh, New Plot, Ambedkar Nagar, MES, Door Darshan and adjoining areas will remain affected on May 12 from 9 am to 1 pm.
Likewise, for replacement of worn out conductor in Sidhra Incomer and Outgoing Bays at Grid Station Sidhra, the power supply to Janipur, Jhajjar Kotli, Sidhra, Bahu Fort and adjoining areas will remain affected on May 12 from 6 am to 11 am.
Similarly, for execution of works under PSDF scheme and routine maintenance of Grid Station equipments and 132 KV S/C Transmission line from Janipur-Jhajjar Kotli, the power supply to Jindrah, Phalata, Salal-I, Salal-II, Reasi, Katra, SMVDU and adjoining areas will remain affected on May 12 from 6 am to 11 am.
Likewise, to carry out work of branch cutting, the shutdown of 33 KV PC-4 line (Bohri-Udheywalla and Machillian section) is being observed.
During the shutdown, the power supply to Lalle-Da-Bagh, Lower Muthi, Laxmi Nagar, Balwant Vihar, Udheywala, Anand Nagar, Machillian, Nagbani and adjoining areas will remain affected on May 12 from 7 am to 1pm. |