Breaking News :   CM Pushkar Singh Dhami resolving Uttarakhand's issues one by one: Amit Shah | Traffic Management is part of holistic Urban Development: IIPA Seminar | Imbibe teachings of Guru Ravidasji for harmonious, just society: Sadhotra | MLA Arvind Gupta inaugurates development works | J&K Bank elevates Ashutosh Sareen, Rajesh Malla Tikoo to CGM posts | Women driving force behind progress of society: Sakeena Itoo | SSP Doda chairs crime/ security review meeting | Tanvir Sadiq chairs review meeting at JLNM hospital | Numaish presents "MIRAGE Pop-Up Show" at Hotel Asia | Directorate of Agriculture Jammu celebrates International Women's Day | Nami Dogri Sanstha felicitated Sandhya Gupta | GDC Bhaderwah celebrated Women's International Day | ADC Bhaderwah reviews progress of Jal Shakti, irrigation works | CRPF 187 Battalion organises blood donation, free medical camp | CUJ organized Extension Lecture on 'Relevance of Fiscal and Monetary Policy in Current Scenario' | Outdoor sports event organized at YCET | MCM holds 2-day workshop on Sustainable Food Practices | Self defence training program held at GDC RS Pura | GDC Ramgarh organizes seminar | "J&K Bank, LFO-BHF organize project RISE | Dream of making J&K nation’s spiritual heart not distant: LG Sinha | LG hands over appointment letter to wife SSF personnel | Dr Farooq pays glowing tributes to Mirwaiz Moulana Muhammad Yousuf Shah | Art 370 abrogation, CAA, Ram Temple key achievements of PM Modi led Govt: Amit Shah | Div Com Kashmir reviews progress of transit accommodation for migrant employees | Good news for Govt employees: 8th Pay Commission begins consultation process | CM Omar stresses on zero casualty goal for linemen, emphasizes proper use of safety gear | J&K Netball Association Announces District-Level Netball Championships | GCW Gandhinagar hosts District-Level Road Safety Awareness Programme | GDC Ramgarh organizes seminar to celebrate International Women's Day | DGP Prabhat reviews security situation in Pulwama | Man arrested for killing his 10-year-old daughter | Affordable medicine initiative reflects Govt’s commitment to ensure accessible healthcare for all: PM Modi | Illegal Mining razed J&K’s Sukhnag River: Govt Report | Army holds ‘Synergy’ Conference with ITBP, BSF | Mortar shell defused in Poonch | Attempts to smuggle phones inside Doda jail foiled | Domestic LPG cylinder costlier by Rs 60 | Bandipora-Gurez Road closed | Rajeshwari Chatterjee – A Pioneer Woman Scientist of India | World Divided Over Artificial Intelligence [AI] | Strengthening Public Health: The Strategic Evolution of the Janaushadhi Pariyojana for Affordable and Quality Generic Medicines | Govind Ballabh Pant took several steps for development, reform of UP: Yogi | DC Anantnag holds interactive meet with Media Fraternity | 170 Military Hospital organises blood donation camp | Steps toward Industrial Revolution in Bundelkhand, rapid progress in land acquisition | 5-day CBP on Transformative Teaching Strategies concludes | Enhancing Synergy for national security | PK seeks medical seat reservation in UP for displaced Kashmiri Pandit students | Back Issues  
 
news details
‘Tawi River Front project to be completed next month’
3/11/2025 11:04:41 PM
Early Times Report

Jammu, Mar 11: Minister for Jal Shkati, Javed Ahmad Rana, today informed the House that the Tawi River Front Project (Phase 1) shall be completed in April, 2025 with an allotted cost of Rs 143.00 crore. The Minister was replying to a question raised by Arvind Gupta in the Legislative Assembly.
He informed that 96 percent and 94 percent physical progress has been achieved on the left bank and right bank of the river respectively.
“The works have been taken up with an estimated cost of Rs. 64.80 crore and Rs. 36.15 crore have been expended, so far.”

Regarding the Tawi Barrage works, the Minister said that the works have been taken up with an estimated cost of Rs. 64.80 crore and Rs. 36.15 crore have been expended, so far. He said that 85 percent of the works of Tawi Barrage and Artificial Lake stand completed.
The Minister said that in order to prevent the direct drain discharge into the Ranbir Canal, a detailed DPR for an amount of Rs 34.06 crore has been prepared for execution of 10 works.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU