Breaking News :   Vikar Rasool likely to face action for “sabotaging” Karra’s rally at Ramban | CM Omar holds public darbar in Ganderbal | J&K Police register first electronic FIR | Jammu: SFs launch searches at multiple places | GOC Sachdeva chairs multi-agency security review meeting | Need new legal framework to regulate harmful content: I&B Ministry | PM Modi to attend Mauritius’ National Day celebrations | CBI books 3 Railway officials | Maha Kumbh: 60 crore devotees take holy dip | Jammu labourer among 8 trapped inside collapsed tunnel | Terrorist hideout busted in Reasi | 6 Assistant Directors shifted in ED | Kashmir schools to reopen on Mar 1 | Soldier injured in landmine blast | Patwari suspended | Migrant labourer found dead | Temperature rises in J&K | District Admin Kupwara holds Mega Workshop | DC Baramulla Inspects Developmental Works | SMVDIME conducts BLS & ACLS provider course for Faculty, Staff | NABARD organizes three-day ‘Tarang Mela’ in Katra | SMVDU NCC Coordinator Represents Institution at Aero India 2025 | SKUAST-Jammu hosts sessions on Agri-Tech careers | JKSCERT Concludes Inclusive Education Training Across Jammu Division | SKUAST-Jammu hosts sessions on Agri-Tech careers | SKUAST-Jammu hosts sessions on Agri-Tech careers | SKUAST-Jammu hosts sessions on Agri-Tech careers | JKSCERT Concludes Inclusive Education Training Across Jammu Division | Power Shut down | Public intoxication offenders sentenced to community service under BNS 355 | Karra asks BJP to clarify it’s stand on statehood | Kashmir Shawls, Carpet lead in exports | Yogi Govt gears up for seamless crowd management ahead of Mahashivratri Snan | Yogi Govt gears up for seamless crowd management ahead of Mahashivratri Snan | Meeting between protesting farmers, central team underway in Chandigarh | GDC Neeli Nallah Udhampur Celebrates 75 Years of Indian Constitution | Cambridge hosts Sahodaya Inter-school Quiz Competition | Department of MSCM Organises Professional Development Programme | GDC Sunderbani Organize Plantation Drive | Tree Plantation Drive Organised at Parat, Rajouri | GDC Thannamandi organizes Thematic Talk cum Panel Discussions | FICCI FLO JKL TB Eradication Drive: Distributes 1350 Nutrition Kits | Three Public Intoxication Offenders Sentenced to Community Service | Back Issues  
 
news details
Sordid saga of Jehangir Chowk-Rambagh flyover
Minister sets deadlines, forgets them later
3/16/2018 11:28:20 PM
Early Times Report

Jammu, Mar 16: The dilatory mode of functioning in the state government could be gauged by the fact that with just two weeks away from the set deadline, the completion of much hyped Jehangir Chowk-Rambagh is far from completion.
As per the insiders, it was impossible that the project would get completed in mere 14 days as the deadline was set by the government as March 31, 2018. "It remains to be seen what would be the new deadline for the completion of the project as merely 60 percent of the work is finished with rest going on at a snail's pace. The government itself seems be clueless as the delay is taking heavy toll on vehicular movement in the summer capital," said an official privy to the development.
Last year in November, labourers and technicians had gone on strike at the site for their pending wages. Due to such a development, the project missed the deadline of its first phase which was earlier set as December 31, this year. The project, on which work began in 2013, is funded by Asian Development Bank (ADB) and executed by Economic and Reconstruction Agency (ERA). The 2.4-km flyover missed many deadlines due to dispute with shopkeepers, floods in 2014 and 2016 uprising. Its completion is expected to reduce the travelling time from Jehangir Chowk to Hyderpora and will ease traffic jams in the city.
Meanwhile, appending wide scale backlash over snail's pace work, the government has tasked the Divisional Commissioner Kashmir to personally monitor the work over the fly over.
Reports inform that the R&B is being slammed by one and all in Valley over the way it is monitoring the work of the flyover- the construction of which has led to total chaos in the summer capital- resulting in traffic mess and prolonged snarls.
Interestingly, the incumbent R&B minister while setting one more deadline had stated that the first link of the flyover connecting Amar Singh College with Barzulla will be operational by the end of August 2017. However, the Div Com in November stated that the first link will get operational by the end of 2017.
Recently, a high level meeting was held in Srinagar that was chaired by the Div Com Kashmir. It was informed in the meeting that the total cost of the Jehangir Chowk-Rambagh flyover project was Rs 262 crore and the first phase of the project from Rambagh-Amar Singh College would be completed by ending December 2017.
Taking the control now in his own hands, the Div Com directed contractors to enhance the scale of labour at the site so that the project is completed in a fixed timeline.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU