KISHTWAR, Apr 1: Chairman Chenab Valley Power Project (P)Ltd, Suresh Kumar today reviewed the progress of execution of various works in Pakkal Dul, Kwar and KERU HEPs in a meeting with officers of District administration and Project Authorites here at DC office Complex Kishtwar. The meeting was attended by Deputy Commissioner Kishtwar, Ashok Sharma, M.D CVPP A.K Chaudhary, ADDC Mohd Hanief Malik, ADC Kishtwar Pawan Parihar, ASP Kishtwar Mushim Ahmed, ACR Kishtwar Dr Amir Hussain, CGM CVPP P.B Jain besides other district officers. During the meeting Chairman took first hand appraisal of the status in the implementation of the RR plan at various power projects of district Kishtwar under construction through CVPP. While reviewing the status of the land acquisition under Pakal DUL HEP, Chairman was informed that the Pakal Dul HEP involves a total of 3556 kanals and 7 Marlas of land with award amount of Rs 99.8 crore, out of which Rs 94.77 stands deposited by intending department and Rs 90.67 crore has been paid so far.
|