Breaking News :   Vikar Rasool likely to face action for “sabotaging” Karra’s rally at Ramban | CM Omar holds public darbar in Ganderbal | J&K Police register first electronic FIR | Jammu: SFs launch searches at multiple places | GOC Sachdeva chairs multi-agency security review meeting | Need new legal framework to regulate harmful content: I&B Ministry | PM Modi to attend Mauritius’ National Day celebrations | CBI books 3 Railway officials | Maha Kumbh: 60 crore devotees take holy dip | Jammu labourer among 8 trapped inside collapsed tunnel | Terrorist hideout busted in Reasi | 6 Assistant Directors shifted in ED | Kashmir schools to reopen on Mar 1 | Soldier injured in landmine blast | Patwari suspended | Migrant labourer found dead | Temperature rises in J&K | District Admin Kupwara holds Mega Workshop | DC Baramulla Inspects Developmental Works | SMVDIME conducts BLS & ACLS provider course for Faculty, Staff | NABARD organizes three-day ‘Tarang Mela’ in Katra | SMVDU NCC Coordinator Represents Institution at Aero India 2025 | SKUAST-Jammu hosts sessions on Agri-Tech careers | JKSCERT Concludes Inclusive Education Training Across Jammu Division | SKUAST-Jammu hosts sessions on Agri-Tech careers | SKUAST-Jammu hosts sessions on Agri-Tech careers | SKUAST-Jammu hosts sessions on Agri-Tech careers | JKSCERT Concludes Inclusive Education Training Across Jammu Division | Power Shut down | Public intoxication offenders sentenced to community service under BNS 355 | Karra asks BJP to clarify it’s stand on statehood | Kashmir Shawls, Carpet lead in exports | Yogi Govt gears up for seamless crowd management ahead of Mahashivratri Snan | Yogi Govt gears up for seamless crowd management ahead of Mahashivratri Snan | Meeting between protesting farmers, central team underway in Chandigarh | GDC Neeli Nallah Udhampur Celebrates 75 Years of Indian Constitution | Cambridge hosts Sahodaya Inter-school Quiz Competition | Department of MSCM Organises Professional Development Programme | GDC Sunderbani Organize Plantation Drive | Tree Plantation Drive Organised at Parat, Rajouri | GDC Thannamandi organizes Thematic Talk cum Panel Discussions | FICCI FLO JKL TB Eradication Drive: Distributes 1350 Nutrition Kits | Three Public Intoxication Offenders Sentenced to Community Service | Back Issues  
 
news details
Bridges worth Rs 43.95 Cr held up due to lack of proper survey
PAC pulls up PWD on its working
2/26/2018 11:01:13 PM
Arun Singh

Early Times Report
Jammu, Feb 26: Lack of due diligence in conduct of site surveys and in finalization of design on the part of Public Works Department resulted in 18 works of construction and reconstruction of bridges valued Rs 43.95 crore in the State held up due to design change or land disputes after awards of works rendering unfruitful expenditure of Rs 26.92 crore.
The Committee on Public Accounts for the years of 2016-17, 2017-18, took serious note on the working of Public Works Department in its reports saying that department didn't follow the set norms while execution of works. "As per Rule 9-3 of Jammu & Kashmir Financial Code (Vol-I) which stipulates that no works should be commenced until a properly detailed design and estimate has been sanctioned and funds to cover the charge during the year have been provided by the competent authority," it said.
Committee castigated the department for not releasing funds for construction of foot suspension bridge at Margi Warwan Kishtwar, steps taken for release of balance funds required for completion of the bridge, the reasons for change of design of overhead pedestrian crossing bridge at Khanabal and suspension bridge to motorable bridge over Nallah Phoru, Baramulla, steps taken for resumption of work on the Khanabal bridge, the reasons for non execution of balance work of the bridge over last five years.
But during scrutiny, Committed noticed that projects valued at Rs 43.95 crore under PMGSY and NABARD were held up due to changes in design after approval of works or due to lack of encumbrance free site which indicated lack of due diligence in site survey and designs at the technical approval stage. Consequently, expenditure of Rs 26.92 crore i.e. 61% of estimated cost of the works was rendered unfruitful. The Department failed to satisfy the committees with its replies as a result, Committee on Public Accounts constituted two Sub-committees in order to discuss the issues with the direction to submit its report to the Committee on Public Accounts for its perusal.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU