Breaking News :   CM’s Appeal | Cong high command ignores ‘Fact-Finding Committee’ report on Assembly poll debacle | Delhi-Srinagar passengers to bridge trains at Katra: Railway Minister | Ex- serviceman killed in Kulgam terrorist attack, his wife, niece injured | CM Omar lauds J&K, Ladakh NCC cadets for exemplary performance | CM advises INDIA alliance to discuss strategy | NC committed for people’s welfare, women’s empowerment: Dr Farooq | Main accused among 5 persons arrested | CB books 5 for duping Jammu residents of Rs. 2.95 cr | Srinagar Police file chargesheet against 7 terror accomplices | Govt working on uniform toll policy: Gadkari | Motorcyclist killed in Jammu accident | Man arrested for opening fire | Jammu Bridges Turn Pink: FICCI FLO JKL, Fortis Hospital Gurugram & JMC Unite for Cancer Awareness | Anand Jain takes over as ADGP Armed J&K | Head priest of Ram Temple in Ayodhya critical after brain stroke | Forest Minister directs for aligning development with environment conservation | Sadhotra seeks special central economic, employment package for J&K | NIA opposes interim bail plea of jailed J&K MP Rashid Engineer in HC | GRAP 3 curbs revoked in Delhi amid dip in air pollution | Substantial increase in budget allocation to states such as Delhi, Bihar, MP, others: Vaishnaw | Jewar Airport to start regular operations from April: Aviation Minister | Bhim Sen Tuti-IPS takes charge as IGPJammu zone | Kavinder condemns cowardly terror attack in Kulgam | Dy CM releases JKBOCWW Board compendium | Sakeena Itoo reviews progress of SAMAGRA Shiksha in J&K | HC give additional charge of Sales Tax Tribunal | LG Manoj Sinha addresses South India Bhu Alumni Meet at Hyderabad | CBI books then Commandant CRPF & Ors | Amit Shah slams Kejriwal, Sisodia; says AAP gave only garbage, toxic water to Delhi | MP Gulam Ali criticizes Kejriwal, promises reforms for traders and SIT on corruption | 2 Crore People Take Holy Dip At Maha Kumbh On Major Day Of Basant Panchami | CBC organizes Swachhta Action Programme | Tony slams Union Budget, calls for Rati Sarari's promotion as tourist spot | Samba police works out theft case; arrested accused, recovered stolen items | Samba police reunites missing girl with family | DC Rajouri inspects structures affected by NH construction | Plantation drive conducted on Doda-Ghat Road | Samba police nabbed drug peddler, recovered 4.76 grams heroin like substance | All J&K Sadguru Kabir Sabha emphasizes community unity, Welfare | AYUSH Department organises awareness program at SAR Institute-Ramban | Congress convenes monthly meeting at Congress office Jammu | Mother India Sr Sec School bids farewell to class 12 students | Crescent Public School hosts Graduation Ceremony for Class 10 | Five-day skill development programme on soft computing begins at SMVDU | MCM organises sensitisation programme on drugs | GDC RS Pura celebrates World Wetlands Day at Gharana Wetland | GGM Science College hosts poster-making competition | GDC Kathua celebrates World Wetlands Day 2025 | Back Issues  
 
news details
117 PHE, I&FC works taken up under Languishing Projects scheme
DDC reviews pace of progress
9/2/2019 9:29:35 PM
Early Times Report

RAJOURI, Sept 2: As many as 117 PHE, Mechanical and I&FC, works are being executed under Languishing Projects scheme across Rajouri district.
The information was given here at a meeting convened to review progress on these languishing projects of PHE, Mechanical and I&FC, sectors with the District Development Commissioner Mohammad Aijaz Asad in the chair.
The meeting was attended by Superintendent Engineer PHE Manish Bhatt, Executive Engineer PHE Nowshera division, Gurvachan Singh, Assistant Executive Engineers, Junior Engineers and others.
The SE PHE informed that work on 29 schemes is on under languishing Project in Rajouri division at an estimated cost of Rs 35.47 crore. He gave a detailed account of all the schemes like filtration plants, laying of distribution network, Suntanks, pipe work etc in different areas of Rajouri division. Regarding Nowshera division, the Executive Engineer PHE Nowshera Gurvachan Singh said that 32 schemes are under execution in Nowshera division costing Rs 24.40 crore. It was informed that the work on all languishing projects of Rajouri and Nowshera division is likely to complete by the next financial year.
The meeting was further informed that out of 13 schemes of I&FC taken up in the district work on 3 has been completed , while others are on different phases of execution.
About PHE Mechanical, the concerned officer informed that out of 43 schemes, 32 have been completed and the work on the rest will start after the procurement of required machinery.
The DDC asked for introduction of composite tendering of different projects to elicit better response from the contractors. He asked them to bring in notice of district administration issues, if any, impeding the execution of work.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU