Early Times Report
JAMMU, June 8: Chief Engineer (Distribution) JPDCL, Jammu has informed that for installation of 11KV VCB Panel at 33/11KV Receiving Station Sidhra, the shutdown of 33/11KV Receiving Station Sidhra is being observed. During the shutdown, the power supply to Sidhra and adjoining areas will remain affected on June 10 from 10 am to 1 pm. Similarly, to carry out conductor stringing work at existing 33/11KV R/Stn, the shutdown of 33KV Lines is being observed. Likewise, the power supply to Pargwal, Channi Tanna, Rajpura, Bhalwal Bharat, Dhalwal Miulu, Hamipurkona, BSF and adjoining areas will remain affected on June 10 from 8 am to 12 noon. Similarly, the power supply to Gharota, Ranjan, Navodya, Amb, Vidyalaya and adjoining areas will remain affected on June 9 and 11 from 8 am to 1 pm
|