Breaking News :   Ministerial ambitions drive Cong MLAs to oppose NC alliance exit | Fact-finding committee submits report on party’s poor show | Train to Kashmir may face few months delay: Farooq | Budhaal remains on edge, 4 more hospitalised | Budhaal declared containment zone | ‘Brain involvement common factor in all deaths’ | CM Omar meets delegations in Jammu | Gulmarg gets more snow | CB books 6, including J&K Bank employee, for duping job aspirants | Centre to establish 100 new Sainik schools: Rajnath Singh | Army open fire on Pak drone | Over 100 sheep charred to death | New Sainik Schools | BJP will emerge victorious in Delhi assembly elections: Vikram Randhawa | Modi Govt empowers women, making them equal partners in Nation's Development: Kavinder | MLA Arvind calls on CM Omar Abdullah, discusses key issues of Jammu West | Amit Shah speaks to Maharashtra CM; takes stock of train accident | Dy CM conducts public darbar at Sana | Snap Traffic Naka in South Jammu City leads to seizure of 15 vehicles | Sakeena Itoo reviews Social Welfare Schemes, highlights vision of health equity | Javed Rana chairs meeting of forest department; asks for streamlining of HR management | Divisional Commissioner, ADGP visit Badhaal village to review safety measures | MP Gulam Ali expresses concern over outbreak in Rajouri | India faces threat from within, not outside: Farooq Abdullah | J P Nadda highlights milestones of Beti Bachao Beti Padhao on 10th anniversary | Power shut down in several areas | Court rejects bail of NDPS smuggler | Amitabh Bachchan celebrates 25 years of Kaun Banega Crorepati with Vinay Gupta from J&K | Over past decade, Beti Bachao Beti Padhao has become people-powered initiative: PM Modi | UP govt nod to new Aerospace and Defence Policy, FDI reforms | Over 150 special trains to run for Maha Kumbh on Mauni Amavasya | SCERT Jammu concludes 3 day workshop on human values | CBC Poonch organises Swachata Awareness program | World Forum for Art and Culture invites Padamshri Balwant Thakur | Notorious drug peddler arrested with heroin in Udhampur | LIC employees demand immediate recruitment in class-3 & 4 cadre | Bailey Bridges inaugurated in Shyok-Nubra Valley | Indian Army organised Mobile Medical Patrol | Dewan Devi Public School celebrates Ram Mandir Anniversary | Jodhamal students win State Level Wild Wisdom Global Challenge | Students of GCW Bhagwati Nagar Excel at Inter-Zonal Competitions | Road Safety Awareness cum Symposium organized | LPU triumphs in 2024-25 Weightlifting Championships | Desh Bhagat University launches Dr Manmohan Singh PhD Fellowship programme | GDC Nagrota organizes awareness programme | Government Polytechnic Jammu hosts seminar | Awareness lecture on various academic application software held | GDC Thannamandi organizes Road Safety awareness program | Awareness seminar on PM Surya Ghar Muft Bijli Yojana organized | Back Issues  
 
news details
DDC Rajouri inspects progress on GMC campus building
Sets Oct 31 deadline for completing academic-administrative block
9/6/2020 10:49:03 PM

EARly times REport

RAJOURI, Sept 6: District Development Commissioner Rajouri, Mohammad Nazir Sheikh on Sunday inspected progress on Government Medical College campus building.
The construction work on the campus is being executed by the Public Works Department. The DDC was accompanied by Superintending Engineer PWD, Bisharat Gelani Bhatt; District Statistical and Evaluation Officer, Bilal Rashid Mir; Assistant Executive Engineer, Mohammad Ashraf and Junior Engineer, Shariq Mir.
The Superintending Engineer PWD informed that the total estimated cost of the project is Rs 139 crore, including Rs 69 crore of the Academic and Administrative block, Rs 40 crore of the residential and hostel block and Rs. 30 crore of the allied works.
He further informed that the structure work on the project is complete in all respects and the finishing work is in progress which is scheduled to be completed by the end of December 2020. It was also highlighted that the work on the approach road is under execution and the work of black topping of the said road shall be completed by end of October,2020.
The DDC directed the concerned authorities to speed up the work on the project and called for execution of work in double-shift to complete the academic and administrative block in all respects by the end of October,2020, so that these are made functional to enable the people to avail the benefit in term of medical services. He also asked for completing the work of black topping on the approach road within shortest possible time.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU