Breaking News :   Celebrating Diwali | Over one million bogus beneficiaries removed from subsidized ration lists | Can’t compromise even an inch on our borders: PM Modi | Disengagement process in certain areas complete: Rajnath Singh | CM Omar Abdullah extends Diwali greetings | DSEK changes school timing | GAD issues parking guidelines | Satish Sharma flags off buses, assures DA for JKRTC employees | ADGP Jammu Zone greets people on Diwali | Sakina Masood inspects construction site of GMC Handwara | Delhi’s air quality deteriorates to ‘very poor’ on Diwali | Amit Shah inaugurates 1100-room rest house at renowned Hanuman Temple in Gujarat’s Botad | Centre's Ayushman Bharat scheme exists only on paper: Delhi health minister | Satellite images show North Korea dug large border trenches after demolishing road, rail links | LG Sinha commemorates Sardar Patel on Rashtriya Ekta Diwas | BLSKS celebrates “Rashtriya Ekta Diwas” | JKCIP meeting held to boost agriculture and allied sectors | NHPC observes 'Rashtriya Ekta Diwas' | SKUAST-TAJ felicitates Prof BC Sharma | SSP Railways Jammu holds security meeting | Training Program for CPIOs Concludes at SKPA Udhampur | National Unity Day observed | ACB holds two mega events at Rajouri, Jammu | Vehicle seized in Jammu for forest produce transport violation | GRP Jammu bids farewell to retiring police personnel | Congress observes Indira Gandhi's Martyrdom Day | Back Issues  
 
news details
Chief Secy expresses dismay over unsatisfactory work on Jammu-Srinagar National Highway
7/27/2021 12:14:22 AM
Early Times Report

Jammu, July 26: As travelling on the Jammu-Srinagar highway has become a highly risky job due to the worst condition of the roads, Chief Secretary, Dr. Arun Kumar Mehta on Monday chaired a meeting to review the status of the highway and took stock of the ongoing road-widening works especially in district Ramban.
Administrative Secretaries of departments of Revenue, Power Development, Public Works (R&B), and Forest, Ecology & Environment, besides District Development Commissioner (DDC), Ramban, SSP Traffic, National Highway, Ramban, Regional Officer, NHAI, and concerned officers participated in the meeting.
As per the official handout of the government, expressing concern, the Chief Secretary observed that the rate of progress of road-widening/maintenance works is unsatisfactory which is causing inconvenience to the commuters. “The problem is further aggravated by rash and in-disciplined lane driving leading to frequent traffic jams; shortage of traffic personnel deputed on NH duty and unannounced movement of army convoys”, he added.
To improve traffic management on the National Highway, the Chief Secretary directed the traffic police to double the manpower to manage traffic at all choking points in addition to implementing suitable remedies to reduce the travel time between Jammu and Srinagar which currently varies from ten to twelve hours on account of mismanaged traffic.
Travelling on the Jammu-Srinagar highway has become a nightmarish experience as the condition of the road has gone from bad to worse due to ongoing widening work. Condition is further compounded due to recent rains and land sliding.
The sinking of patches and huge landslides between Ramban and Banihal have reduced the road to half at over a dozen places which causes jams and frequent traffic disruptions giving a tough time to travellers.
Closing high-way due to landslides has become a routine affair.
To further streamline traffic movement on the highway, the Chief Secretary directed NHAI and DDC Ramban to develop various vehicle holding areas at Kainthi, Karol, Kowbagh near Ramban town, Peerah, Asher, near Banihal, and Ramsoo; to accommodate stranded vehicles in the event of closure of the national highway due to bad weather.
He further directed the installation of LED signage at all critical locations along the entire stretch from Jammu to Srinagar within one week to provide real-time information on the current traffic position to the commuters to help them decide the future course of their journey.
Regarding traffic movement through the new ‘Navuyug’ tunnel at Banihal, the DDC, Ramban was directed to immediately operationalize both tubes of the tunnel for passage of civilian traffic.
The Chief Secretary directed the NHAI to complete the macadamization of Dalwas stretch in 3 days and Jakheni-Nashri section by 15th August 2021, besides immediately commencing the realignment works on Ramban-Banihal section to be completed by December 2022.
NHAI was also directed to handover the by-pass section of old NH – Pantha Chowk-Sonwar road to PW(R&B) Department for its further maintenance.
The NHAI was further asked to install crash barriers with warning signs at all critical junctions by 31st August 2021 to prevent fatal accidents on the National Highway-44.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU