Power shut down
12/26/2015 10:44:59 PM
JAMMU, Dec 26: In order to carry out the work for erection of beam structures in existing bay and stringing of conductor of 11 KV O/G feeder, Rakh Muthi at 33/11 KV Receiving Station Burmal by M/s IRCON International Ltd under Cluster-IV R-APDRP Part-B, the shutdown of 33 KV Jourian I/C line emanating from 132/33 KV Grid Station Akhnoor on December 27, 2015 from 09:30 AM to 04:30 PM is allowed.
The areas to be affected during the shutdown period included Burmal, Devipur, Rakh Muthi, Sohal Bhalwal, Jourian, Sohal, Rakh Malal and Essential 11 KV feeder of BSF, MES & PHE.
Similarly, to carry out the work for PCC Pole insertion and 11 KV reconductoring as 11 KV (K-02) feeder is passing under the 33 KV New Kartholi feeder near 33/11 KV Receiving Station Katholi (EPIP), the shutdown of 33 KV Kartholi (EPIP) feeder on December 27, 2015 from 09:00 AM to 01:00 PM is allowed.
The areas to be affected during the shut down period included Industrial area of EPIP Kartholi and Bari Brahmana.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU