TD executing wing violate Codal formalities
Exceeds power limits up to 1000 % of original estimates
12/26/2015 10:46:53 PM
Arun Singh
Early Times Report

Jammu, Dec 26: Some senior officers of the Executing Wing of Tourism Department exceeded their powers while carrying out various construction works for tourism department across the state in excess of the original estimates without following the Codal formalities.
Sources told Early Times that there are standing norms of exceeding the work of original estimates upto 5 % but strangely, the executing wing of Tourism Department carried out over 200 construction works by exceeding their powers vested with it ranging 6% to 1000% thereby undauntedly violating the extent of 5% allowed to the exceeding wing on the original estimates approved by the department.
"As per the delegation of financial powers, the Chief Engineer, Superintending Engineers and Executive Engineers are empowered to sanction excess to the extent of five per cent over the original estimates. But it was found that excesses over original estimates had been allowed beyond the permissible limit of five per cent in 213 works and the excess ranged between six to 1000 per cent in disregard of the above provisions," they alleged.
Shockingly, the execution of additional/ extra quantities of different components of works against sanctioned estimates was allotted on approval basis to the same agencies/ contractors beyond the permissible limits without ensuring competitions through tendering process, they maintained.
In order to substantiate the statement of facts, an example was cited in case of Pahalgam Development Authority where total 15 works were carried out having original cost Rs 3.44 crore as per approval but the executing wing went to the extent of incurring an amount of rupees Rs 4.60 crore which were spent exceeding 12 to 316 percent limit vis-a-vis five percent.
Similarly in case of Surinsar-Mansar Development Authority three construction works were carried out having original cost of Rs 32.22 lakh as per approval but Rs 59.85 lakh were spent exceeding 29 to50 percent. In case of Lakhanpur Sarthal two works were given approval 20 to 36 percent.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU