Early Times Report SRINAGAR, June 14 : According to Power Controller, Power Development Department, Kashmir, in order to carry out branch cutting, stabilization works and shifting of conductor/link set from Old PCC poles to newly erected 11 meter long poles at Bagh Ali Mardan Khan for smooth functioning of power supply from the 33 KV line from Habak-Lal Bazar-Kathi-darwaza and Habak-BAMK lines shall be affected on June 15, 2015 from 9 a.m to 6 p.m. respectively. Meanwhile, in another communication from the PDD, in order to expedite the construction work on 2x10 MVA Receiving Station, power supply from the 33 KV Shadimarg line shall be affected on June 14, 2015, power supply from the 33 KV Reshipora line shall be affected on June 21, 2015, power supply from the 33 KV Pulwama line shall be affected on June 21, 2015 and power supply from the 33 KV SIDCO lines shall be affected on June 14 and June 21, 2015 from 9 a.m. to 6 p.m. respectively. The power supply to these areas fed from these lines shall remain affected on the said dates and time. |