Jammu, July 18:In order to carry out the construction works under R-APDRP scheme, the power supply to Janipur Colony, Lakkar Mandi, Pamposh Colony, Lower Roop Nagar and Muthi PHE Line being fed from J-2, J-3, RN-3 and MU-10 feeders shall remain affected on July 20, 22, 24, 26, 28 and 30 from 6 am to 10 am. Meanwhile, to carry out the construction works under R-APDRP scheme, the power supply to Toph, Talab Tillo, Manorma Vihar, Udheywala, Om Nagar and its adjoining areas being fed from T-2, T-3, T-4 and T-5 feeders will remain affected onJuly 20, 22, 24, 26, 28 and 30 from 6 am to 10 am. However, to carry out stringing work between location no 41/0 and 42/0 on 11 KV lines coming under 400 KV D/C Samba-Amargarh Transmission Line, the power supply to Gho Manhansa, Lorichak, Sangwan etc shall remain affected on July 20from 5 am to 12 noon. |